EXPLAINING THE PLAN – Debbie Hartman, a consulting engineer for Somerset County, explains the proposed plan for the Griggstown Causeway that is hoped will improve safety and reduce traffic congestion. Somerset County officials on July 1 unveiled a $2 million project that is hoped will alleviate traffic congestion problems at the Griggstown Causeway. If approved, the plan would not come …
Read More »Updated Status Of Various Street Resurfacing Projects
The following is an update of road work projects in the township. Newkirk and Evergreen Resurfacing – Concrete work is in progress. Weather permitting milling and paving will begin when concrete work is completed. Rodgers Ave Area Resurfacing -All paving completed. Restoration and striping still to be completed. Rodgers Ave – Paved Waldorf St – Paved Hunt Rd -Paved Continental …
Read More »Street Resurfacing Projects Updated
Newkirk and Evergreen Resurfacing -Concrete work to begin on or about June 16, weather permitting. Milling and paving will begin when concrete work is completed. Rodgers Ave Area Resurfacing -All paving completed. Restoration and striping still to be completed. Rodgers Ave – Paved Waldorf St – Paved Hunt Rd -Paved Continental Rd -Paved Elmwood St -Paved Holly St – Pavved …
Read More »Township Road Work Update
Newkirk and Evergreen Resurfacing Concrete work to begin on or about June 9, weather permitting. Milling and paving will begin when concrete work is completed. Rodgers Ave Area Resurfacing All paving completed. Restoration and striping still to be completed. Rodgers Ave – Paved Waldorf St – Paved Hunt Rd -Paved Continental Rd -Paved Elmwood St -Paved Holly St – Pavved …
Read More »Township Street Resurfacing Project Status
Here is the latest on the Township’s road resurfacing projects. Newkirk and Evergreen Resurfacing – Concrete work to begin on or about May 28, weather permitting. Milling and paving will begin when concrete work is completed. Rodgers Ave Area Resurfacing – Milling and paving to begin Mid June on Holly St. Rodgers Ave – Paved Waldorf St – Paved Hunt …
Read More »Status Of Township Street Resurfacing Projects
The Township Department of Public Works has issued the following updates to street resurfacing projects. Newkirk and Evergreen Resurfacing -Awarded Rodgers Ave Area Resurfacing -Milling and paving to begin May 12th on Holly St. Rodgers Ave – Paved Waldorf St – Paved Hunt Rd -Paved Continental Rd -Paved Elmwood St -Paved Holly St Victor St -Paved Martin St -Paved Van …
Read More »Reducing Lanes On Part Of Hamilton And Home Streets Among Planned Safety Improvements
PROJECT EXPLAINED – Bruce Klein of T&M Associates, speaks about the proposed improvements to a 1.7-mile stretch of Hamilton Street on March 12. Reducing the number of lanes on part of Hamilton Street from four to three, and making Home Street a one-lane street to ease turns onto Hamilton, were two of the many safety improvements to part of Hamilton …
Read More »SCAP, Township, Offer Construction Certification Program
The Somerset Community Action Program (SCAP) and Franklin Township are offering a construction and carpentry certification training program to Franklin Township residents affected by the Covid pandemic. The program begins March 3, with courses offered 9 a.m. to 2 p.m. Mondays through Thursdays at the Franklin Township Board of Education administration building, 2301 Route 27. The Civil Construction Program is …
Read More »Township Updates Road Resurfacing Program
Here is the December 12 update of the Township’s 2024-25 road resurfacing program. New Brunswick Rd ( Willow to DeMott) -PAVED Home, Ambrose and Dunbar streets Resurfacing -PAVED Rodgers Ave Area Resurfacing – As weather permits concrete work still in progress on Holly St. Paving on Holly St will be in Spring 2025 Rodgers Ave – Paved Waldorf St – …
Read More »Township Road Improvement Update
The Township Department of Public Works has released the latest update to the 2024 road improvement program. New Brunswick Rd ( Willow to DeMott) – NEW BRUNSWICK RD FROM WILLOW TO DEMOTT TO BE CLOSED FOR PAVING 12/9/24 Milling in progress- Paving to start Monday 12/9/24 to 12/11/24. Weather Permitting Home, Ambrose and Dunbar St’s Resurfacing -Concrete work in progress. …
Read More »