PORTION OF ROAD TO CLOSE – New Brunswick Road between Cedar Grove and Wells lanes will close around August 18 for the reconstruction of the Al’s Brook bridge. A 46-year-old bridge deemed to be “structurally deficient” will be replaced later this month, resulting in part of the road being closed into September. The bridge, known as K0607, carries New Brunswick …
Read More »Street Resurfacing Projects Updates
Following are updates on the Township’s street resurfacing projects. Newkirk and Evergreen Resurfacing -Completed
Read More »Township Road Resurfacing Projects Update
Newkirk and Evergreen Resurfacing -Completed Rodgers Ave Area Resurfacing -All paving completed.
Read More »Griggstown Causeway Improvements Unveiled At Somerset County Meeting
EXPLAINING THE PLAN – Debbie Hartman, a consulting engineer for Somerset County, explains the proposed plan for the Griggstown Causeway that is hoped will improve safety and reduce traffic congestion. Somerset County officials on July 1 unveiled a $2 million project that is hoped will alleviate traffic congestion problems at the Griggstown Causeway. If approved, the plan would not come …
Read More »Updated Status Of Various Street Resurfacing Projects
The following is an update of road work projects in the township. Newkirk and Evergreen Resurfacing – Concrete work is in progress. Weather permitting milling and paving will begin when concrete work is completed.
Read More »Street Resurfacing Projects Updated
Newkirk and Evergreen Resurfacing -Concrete work to begin on or about June 16, weather permitting. Milling and paving will begin when concrete work is completed. Rodgers Ave Area Resurfacing -All paving completed. Restoration and striping still to be completed.
Read More »Township Road Work Update
Newkirk and Evergreen Resurfacing Concrete work to begin on or about June 9, weather permitting. Milling and paving will begin when concrete work is completed. Rodgers Ave Area Resurfacing All paving completed. Restoration and striping still to be completed.
Read More »Township Street Resurfacing Project Status
Here is the latest on the Township’s road resurfacing projects. Newkirk and Evergreen Resurfacing – Concrete work to begin on or about May 28, weather permitting. Milling and paving will begin when concrete work is completed. Rodgers Ave Area Resurfacing – Milling and paving to begin Mid June on Holly St. Rodgers Ave – Paved Waldorf St – Paved Hunt …
Read More »Status Of Township Street Resurfacing Projects
The Township Department of Public Works has issued the following updates to street resurfacing projects. Newkirk and Evergreen Resurfacing -Awarded
Read More »Reducing Lanes On Part Of Hamilton And Home Streets Among Planned Safety Improvements
PROJECT EXPLAINED – Bruce Klein of T&M Associates, speaks about the proposed improvements to a 1.7-mile stretch of Hamilton Street on March 12. Reducing the number of lanes on part of Hamilton Street from four to three, and making Home Street a one-lane street to ease turns onto Hamilton, were two of the many safety improvements to part of Hamilton …
Read More »